BACKGROUND
The client required the ability to vary the flow of the water due to the complexities of disposal capacity. The variable speed ability of the generators granted the client flexibility to manage their water demand to suit the environmental conditions.
0
Hours worked LTI-free
Adaman
Client
0
Pieces of equipment
Mid West
Region
0
Billion litres of water
Gold
Commodity
0
Months
Rental
Contract
KEY SUCCESS
UON was contracted to design, manufacture and install a pontoon system to dewater over 7 Billion litres from an old open pit mine within 12 months. The key success of the Pit Dewatering Works was the use of UON’s patent-pending GMC unit for total pumping control where pit access and logistics is challenging.
DELIVERABLES
UON deployed electric pumps powered by our GMC generators to deliver over 30% fuel savings compared to competitors.
- 3 x 300kVA GMC Generators
- 3 x 147kW Pumps
- 3 x UON Modular Pontoon Systems